MMEPL Pre Bid Consultancy for DMRC CC126

 

MMEPL successfully completed Prebid Consultancy Services of DMRC CC126 Project for the client STEC-SUCG for a value of Rs.3350 Million, The subject work Consists of Design and Construction of twin tunnel by Shield TBM. Cut & Cover tunnel box and one UG Station namely Dhansa stand including Architectural finishing, water supply, sanitary installation and drainage works for extension of Dwarka Najafgarh Metro Corridor of Phase-III of Delhi MRTS

Client STEC-SUCG JV won the Tender, LOA issued by DMRC and work is in progress.

The Salient Features of this project are as under: 

  • Study of Tender documents along with the amendments, addendum/ Corrigendum issued by DMRC from time to time as per the context of aforesaid Project.
  • Resolving and formulating  Pre Bid Queries
  • Preparing of Traffic and Utility Diversion Plans as per the given drawings.
  • Reviewing Drawings of 1 Nos. of Underground Stations, Cut and Cover, including GAD etc. and all other drawings related to the project provided by the Clients.
  • Design Review with reference to optimization and Reviewing of Bill of quantities to have competitive bid.
  • Detail working on the Work Program as per the Key dates.
  • Suggestion on CAPEX, Shuttering and Staging Requirement for Project
  • Preparing Casting Yard Layout as per associated costs as well as equipment to be required in casting yard as per tentative area requirement.
  • Preparing Construction Risk Management Plan and Costing of Projects item wise.